Construction project recovery: A late project can be recovered without turning it into a battlefield.
Construction project recovery is bringing a late job back to a date everyone believes in. We do it in four moves: measure where the job really stands, rebuild the programme with the trade partners, resequence for efficiency, and lead the team home. It is how an £11m school, eight weeks behind with seven months left, still finished on its original contract date. The work carries on throughout.
Two Jobs, Recovered Without a Claim
8 weeks → 0
£11m school
Joined eight weeks behind programme with seven months remaining. Delivered on its original contractual completion date.
10 weeks → 2 days
£12m primary school
A late design change stretched the frame package from 10 weeks to 22: a 10-week delay on the critical path. Handed over 2 days late, with no claim.
Neither outcome was achieved through stronger claims. Both were rebuilt with the people doing the work. A recovery plan without buy-in is simply fiction with a deadline. See the full results, case by case →
What Does a Project Health Check and Recovery Plan Cost?
Three steps. You can stop after any of them. All prices plus VAT.
Project health check
£900
One day on your job. An honest measure of where it really stands: programme, sequence, supply chain and what is recoverable. You get a straight position and the first moves.
Recovery plan
£1,800
Two further days at £900 a day. The programme rebuilt with your trade partners, so the dates are theirs.
Led recovery
£900 a week
One day a week with your team, holding the weekly control rhythm, until you are satisfied the job is back.
On our Cost of a Week model, one late week costs about £32,000 on a £10m job and about £54,000 on a £20m job. A recovery that saves four weeks on a £10m job is worth well over £100,000. Put your own job into the calculator →
Recovery Team, More Pressure, or Replace the Contractor?
| Route | What happens | What it tends to cost |
|---|---|---|
| Manage it internally with more pressure | A senior manager is moved across and a recovery programme is demanded by Friday. Sites under pressure hide bad news, and hidden bad news is how a slip becomes a crisis. | The delay you already have, plus the weeks it takes to admit it. In a CIOB survey, 38% of contractors only notified a delay once completion was likely to be affected. |
| Replace the contractor or a key partner | Work stops and the site is re-tendered. | The new team prices the unknown. At Royal Liverpool University Hospital the estimated cost to complete rose from £117m to £293m after its contractor collapsed (NAO, 2020). |
| An independent recovery, with the team you have | An honest baseline from someone outside the job's reporting line, then the programme rebuilt with the trades who will deliver it. Work carries on. | £900 for the health check, £1,800 for the plan, then £900 a week, set against the cost of each late week. |
Can You Recover a Project Without Stopping Work?
Yes. Almost every recovery happens on a live job, and stopping it usually makes the hole deeper.
The work carries on while the sequence is rebuilt around it. What a live recovery runs on is the supply chain: on one school recovery, a drylining partner we had worked with for years put up to 60 operatives on site when we needed them. No rate buys that. A relationship does.
The one thing worth stopping is the team, for a day, to rebuild the plan together. It is usually what makes the new plan stick.
Four Moves, In That Order
Skip the first and every move after it stands on sand. Do them in order and the job comes back without becoming a battlefield.
Measure the truth
Establish an honest understanding of the project's real position before making recovery commitments.
Rebuild with the partners
Recovery programmes are built with the supply chain involved directly, not imposed from above.
Resequence for efficiency
We reorganise work around efficiency, prepare work areas properly and protect whatever programme time remains.
Lead the team home
Morale, transparency with customers and behaviours that encourage collaboration rather than conflict all matter.
Monitor supply chain health
3,931 construction firms became insolvent in England and Wales in 2025, 56% of them specialist trades (Insolvency Service). We help identify warning signs before problems begin affecting delivery.
Keep it out of court
Maintain accurate records while information remains fresh and visible. The goal is a completed project, not a successful dispute.
This is principle 07 of the Live Programme Method: Recover By Rebuilding, Not By Blaming. Need to re-baseline the programme first? Try the free Programme Generator.
The Most Affordable Recovery is the One Started Early
38%
of contractors in a CIOB survey only notified a delay once completion was likely to be affected (CIOB, 2008).
£117m → £293m
Rise in the estimated cost of completing Royal Liverpool University Hospital after its contractor collapsed (NAO, 2020).
£32,000
What one late week costs on a £10m job, on our Cost of a Week model.
Start Free, Before It Gets Expensive
Check it yourself
Is your project recoverable? Seven questions, and nobody sees the answer but you.
Take the self-checkSend us the programme
A free review of your programme by a CIOB Gold Medal winner. You get a straight read on whether the dates hold.
Ask for a reviewA free planning workshop
For your team, online, half a day at most. Or simply a conversation: no pitch, and a reply within one working day.
Talk to AndyConstruction Project Recovery: FAQs
What is construction project recovery?
Bringing a late or troubled job back to a completion date the whole team believes in, by re-measuring where it really stands and rebuilding the programme with the people who will deliver it.
How much does a project health check and recovery plan cost?
A project health check is one day at £900 plus VAT. A recovery plan is two further days at £900 a day. Leading the recovery is one day a week at £900, for as long as you want it. Set that against a late week: about £32,000 on a £10m job on our model.
How is a credible construction recovery programme developed?
In four moves, in order: measure the truth, rebuild the sequence with the trade partners who will build it, resequence for efficiency rather than for the record, and lead the team that is behind. The first 30 days decide most recoveries.
Can a live project be recovered without stopping construction?
Yes. Recovery happens on live jobs, with the sequence rebuilt around the work. It depends on trade partners willing to put extra labour on when it is needed.
Is an independent recovery team better than replacing the main contractor?
Usually. Replacing a contractor stops the job, and the new team prices the unknown. An independent recovery keeps the team and the work going and fixes the plan they are working to.
When should we call for help?
When the programme stops being mentioned in meetings and dates are defended instead of discussed. The cheapest recovery is the one started while the job still looks recoverable.