Construction project results: Not Theory. Twenty-Three Years of Jobs That Finished.

The method on this site was built on real jobs: delivered early, recovered from serious delay, and run with the supply chain rather than against it. Here is the record.

23Projects personally delivered, £5m to £40m
£1bn+Supply chain spend managed across a portfolio
150Project and senior site managers trained
6 wksEarly on a £22m school, Gold Medal year
Andy Pritchard on stage at the CIOB awards
Gold Medal, 2019CIOB Construction Manager of the Year Awards
Case studies

Three Construction Case Studies That Prove the Method

The Gold Medal project

A £22m School Handed Over Six Weeks Early

The job
A four-storey concrete-frame secondary school on a live school site, delivered in seven sectional completions. Internally, the programme was considered extremely tight.
What made the difference
All the time was won before a spade went in the ground: a programme the whole team built and owned, the approach now taught as the Live Programme Method.
The result
Handed over six weeks and one day early, with the ground floor released twelve weeks ahead of schedule.
Handover against the contract date
Contract programmeContract completion
Actual
6 weeksand one day early
Recovery project

An £11m School Recovered From Eight Weeks Late

The job
Joined the job eight weeks behind programme, with seven months left on the programme.
What made the difference
The programme was rebuilt with the supply chain in the room, working with them rather than against them. How we recover slipping jobs.
The result
Handed over on the contractual completion date.
Forecast finish, joining day to handover
Forecast on joiningContract date
Actual
0 weekslate at handover, from eight weeks behind
Recovery project

A Ten-Week Delay Cut to Two Days, With No Claim

The job
A structural frame failure put the project ten weeks behind on the critical path.
What made the difference
Live resequencing with the trades in the room, so the people doing the work owned the recovery.
The result
Recovered to a two-day variance, with no claim.
Delay on the critical path
After the frame failure
After resequencing
2 daysof variance, down from ten weeks behind
At business scale

Not Just Projects. Whole Divisions.

Before Constructing Culture, Andy spent 18 years at a major UK contractor, finishing as head of supply chain, planning, business improvement and project controls for an interiors division. It is the same work we now do as business improvement for contractors of every size.

Loss to profitThe division moved from loss to profit within 12 months.
18 monthsEvery project on time, or with extensions of time fully funded by the client, for the whole 18 months in charge.
High 50s to 70sPercent Plan Complete (PPC), the share of each week's planned work actually done, rose from the high 50s to the high 70s within 18 months.
£150m+The interiors division whose supply chain, planning, improvement and project controls he led.
£1bn+Supply chain spend managed across a multi-project portfolio.
Recognition

Recognised by the Industry and by the People Who Deliver

CIOB Gold Medal, 2019

Gold Medal at the CIOB Construction Manager of the Year Awards for Woodmansterne School, the £22m school above. See the 2019 winners.

Most Considerate Site in the UK

National winner. The same project scored 47 in the Considerate Constructors Scheme twice, a record at the time. Proof that well-run projects are also better neighbours.

Andy combines data-driven innovation and fearless leadership, a rare talent. A strategic problem-solver who transforms construction businesses.Roger Forsdyke, COO, Willmott Dixon Interiors