Pick the closest building type, enter the floor area and storeys, and press Build my programme. You can change everything afterwards.
A tool gives you a duration. Getting the trades to commit to it is the job. That's the Live Programme Method.
The plan at your chosen rates, with the buffer to the P80 handover date shown at the end. Click a phase name to open or close it.
The chart is wider than the panel: scroll sideways, or
The latest date to place the order and still start on time. Work backwards from delivery: any package whose date has passed is already driving the end date.
Line of balance: each area runs the same sequence. Trades follow each other through the areas at a steady pace, at least a week apart. HOLDHold point: work stops until this is inspected and signed off.
Three top-down checks against the bottom-up build. Each is a range, never a single answer.
Every duration shows its working: quantity ÷ (rate × resources). The rates are starting points for the conversation with your trade partners, not answers.
Adjustment covers height and access, small rooms, complexity and heritage (decorative brick bonds run about 40% slower), congestion and continuity, and winter working. 1.0 is the book norm; 0.7 means the trade achieves 70% of it. Technical lag: time that passes whatever you do, like screed drying. More gangs don't shorten it.
Weather allowance: working days expected to be lost to weather on exposed activities, by month. Shown openly so everyone can see it. The defaults are the average weather-lost working days for open external works in your region, from 30 years of reanalysis data (1991 to 2020): about 2 a month in summer and 5 to 9 in winter. In a bad year (1 in 5) expect 2 to 4 more in winter. For contract purposes, use the Met Office Planning Average report for your site.