Programme generator · v2.9

Programme

Start here

Pick the closest building type, enter the floor area and storeys, and press Build my programme. You can change everything afterwards.

More options
Used only for the sanity check.
Applies to rate-based activities. Fixed durations are already in working days. The CIJC working week is 39 hours.
Sets the bank holidays, the weather calendar and the building control route. The Building Safety Levy applies in England only.
Calendar21 Dec to the first Monday after 1 January (the CIJC dates for 2026/27: finish Fri 18 Dec, back Mon 4 Jan). Bank holidays for your region to 2030 always apply.
Edit activities

Every duration shows its working: quantity ÷ (rate × resources). The rates are starting points for the conversation with your trade partners, not answers.

Adjustment covers height and access, small rooms, complexity and heritage (decorative brick bonds run about 40% slower), congestion and continuity, and winter working. 1.0 is the book norm; 0.7 means the trade achieves 70% of it. Technical lag: time that passes whatever you do, like screed drying. More gangs don't shorten it.

Weather calendar

Weather allowance: working days expected to be lost to weather on exposed activities, by month. Shown openly so everyone can see it. The defaults are the average weather-lost working days for open external works in your region, from 30 years of reanalysis data (1991 to 2020): about 2 a month in summer and 5 to 9 in winter. In a bad year (1 in 5) expect 2 to 4 more in winter. For contract purposes, use the Met Office Planning Average report for your site.

Where the numbers come from