What Do the UK’s New Late Payment Rules Mean for Construction? (2026)
The Commercial Payments Bill would cap payment terms at 60 days (30 for public bodies), make statutory interest impossible to contract out of, give firms 30 days to verify an invoice, and ban cash retentions in construction after a 2-year transition. None of it is law yet. It has passed the Lords and is now before the Commons. The behaviour it targets is already costing you.
Last reviewed: November 2026
Late payment is not a finance problem. It is a site problem that shows up in the finance report.
The government’s Commercial Payments Bill, which it calls the largest crackdown on late payments in over 25 years, puts the cost at £11 billion a year to the UK economy and 38 businesses closing every day (GOV.UK, 19 May 2026). Construction has more insolvencies than any other sector, and more than half of them are specialist trades. This is our industry’s Bill more than anyone’s.
Where it stands (31 October 2026): the Bill finished its Lords stages at third reading on 20 October 2026 and had its first reading in the Commons on 21 October as Bill 166. No date is set for Commons second reading. It can still change. For the retentions ban in detail, read The UK retentions ban, explained for contractors.
What are the UK’s new late payment rules?
Five changes matter to a contractor. All would apply only to contracts made after each part comes into force.
| What changes | What the Bill says | Who it applies to |
|---|---|---|
| Maximum payment terms | 60 days from the payment being due; 30 days where the buyer is a public body. If a contract says nothing, 30 days applies. Longer terms are void. | Business contracts, with exemptions to be set by regulations (see below). Construction contracts are covered |
| Statutory interest | Can no longer be excluded, reduced or delayed by contract, including during a dispute | All contracts in scope |
| Invoice verification | Any acceptance or verification process not finished within 30 days is treated as finished, unless a longer period is fair and reasonable and the buyer can prove it | All contracts in scope |
| Cash retentions | New retention clauses void after a 2-year transition; any retention still held paid back by the last retention day | Construction contracts |
| Small Business Commissioner | New adjudication scheme for payment disputes, investigations into poor payers, penalties up to 1% of annual turnover | Large businesses paying small ones |
What does the 60-day payment cap mean?
The era of 90 and 120-day “strategic” terms is ending. Under the Bill as it stands, a payment term longer than 60 days is void, and public bodies get 30. For construction contracts, the final date for payment must fall within 60 days of the payment becoming due.
The government’s own summary describes a cap on large firms paying smaller suppliers. The Bill text is wider: the cap covers business contracts generally, and the exemptions are to be set by regulations once business sizes are defined, for example where both parties are large, or where the buyer is smaller than the supplier. Ministers would also be able to shorten the 60 and 30 days later, but not lengthen them.
Can contracts still exclude statutory interest?
No. Statutory interest on late payment is already 8% above the Bank of England base rate under the 1998 Act, but today a contract can swap it for a lower “substantial remedy”. The Bill would make any term that excludes, reduces or delays that interest void.
That matters because of who asks for it. The government made interest mandatory because small firms said asking for it risked damaging the relationship with the business they supply. In the government’s own consultation, partners described an imbalance of power that let contractors shape payment practice to suit themselves (BEIS, summary of responses, 2020). The law is being written around the fact that partners won’t complain.
What happens to construction retentions?
The Bill would ban them, in two stages. Retention clauses agreed during a 2-year transition stay lawful, but any retention still held must be paid back by the “last retention day”, 3 years after the rules come into force, including under contracts signed before the ban. New clauses agreed after the transition are void, and so is varying an existing clause after it, unless the change favours the partner.
Whether retention bonds survive is not settled; the Government says it will work with surety providers so products are available. Escrow used only as a way of paying stays allowed, but money a third party holds back as security could itself count as a retention (Gowling WLG, 14 October 2026).
The case for the ban is in the government’s own research. Retention money was used to pay for fixing defects in under 1% of contractors’ contracts, and contractors rated retentions 4.3 out of 10 as protection against defects (Pye Tait for BEIS, 2017). The 5% was never really about quality.
When do the new rules start?
Not yet, and not all at once. Once the Bill becomes an Act, the Secretary of State brings each part into force by regulations, on different days for different parts, and the changes apply only to contracts made after that. Gowling WLG expects Royal Assent in 2027. If the retention rules started that year, new retention clauses would be void from 2029 and the last retention day would fall in 2030. A later start moves both back.
Where the Commercial Payments Bill has got to
- Introduced in the LordsMay 2026
- Second readingLords
- CommitteeLords
- Report15 Sep 2026
- Third reading20 Oct 2026
- House of CommonsFirst reading 21 Oct 2026 (Bill 166). Second reading not yet scheduledYou are here
- Royal AssentExpected 2027 (Gowling WLG)
- CommencementBy regulations, part by part
- Retention transition2 years
- Last retention day3 years after commencement; 2030 at the earliest
Dates from the Bill’s parliamentary record and Gowling WLG (14 October 2026). Later stages have no fixed dates yet.
That is the wrong reason to wait. Partners are already deciding who to work for on exactly these behaviours.
What happens on site when trade partners aren’t paid?
We have always held that payment performance is one of the clearest indicators of project health. When a supply chain isn’t paid on time, the site starts to degrade:
- specialist gangs move to more reliable payers;
- material deliveries get quietly deprioritised;
- trust erodes, and the job fills up with defensive documentation.
Partners don’t just price late payment. They decide whether to turn up at all. A study pooling 24 surveys across 15 countries found payment terms and the client’s payment history among the top four factors in whether contractors bid (Oo, Lim and Runeson, Buildings, 2022). In my experience on the buying side, the contractor who pays fairly gets 5 to 10% better prices for identical work. Not because they negotiate harder. Because their partners trust them enough to sharpen the pencil.
Every good partner keeps a league table of its clients. Your payment record is the first column on it.
Free tool
What does one late week cost on your job?
About £54,000 on a £20m project. Put your own contract value in and see the split.
How should contractors prepare?
Treat payment as an operating measure, not a finance one.
- Measure it weekly, at source. Days to pay by partner, alongside programme and quality, in the same report your project teams already fill in. What you only see monthly you only fix monthly.
- Find what slows payment, then fix the cause. Usually it is late valuations, slow sign-offs or disputes used as a delay. Under the Bill, a verification process longer than 30 days would have to be justified. Tighten sign-off now.
- Count your retentions. Add up what you hold and what is held from you, and release what is already due.
- For large contractors: you already publish payment performance twice a year. The government has said it wants boards or audit committees of persistent late payers to explain their record; that is not in the Bill itself, so watch the reporting regulations. Treat it as governance either way, because public clients already ask.
- For Tier 2s and specialists: keep evidence and sign-offs tight, so a dispute cannot become a delaying tactic, and know that interest will be yours by right.
If cash is tight because jobs overrun, the problem starts upstream: see how we embed business improvement, or put a price on a late week with the Cost of a Week calculator.
The bottom line: the law will make you pay on time. Your partners will remember whether you did before it had to.
Related reading: becoming a contractor of choice and retentions and supply chain trust before the ban.
Three free ways to start
A conversation
Tell Andy what you want to change. No pitch, and a reply within one working day.
Book a conversationA free planning workshop
For your team, online, half a day at most, on a live job of yours.
Ask about a workshopA free programme review
Send a programme. A CIOB Gold Medal winner tells you whether the dates hold.
Ask for a reviewFAQs
What are the new UK late payment rules for 2026?
The Commercial Payments Bill would cap payment terms at 60 days (30 for public bodies), make statutory interest non-excludable, set a 30-day limit on invoice verification and ban cash retentions in construction. It is not yet law.
Is the 60-day payment cap law yet?
No. The Bill passed the Lords on 20 October 2026 and is now in the Commons. Each part starts on a date set by regulations after Royal Assent, and applies only to new contracts.
Does the 60-day cap apply to construction?
Yes. For construction contracts, the final date for payment would have to fall within 60 days of the payment becoming due, or 30 days where the buyer is a public body.
Can a contract exclude statutory interest?
Not under the Bill. Any term that excludes, reduces or delays statutory interest, currently 8% above base rate, would be void.
When will cash retentions be banned?
New retention clauses would be void 2 years after the retention rules start, and any retention still held would have to be paid back after the last retention day, 3 years after they start. The start date is not set. If it were 2027, the earliest possible, those dates would be 2029 and 2030 (Gowling WLG expects Royal Assent in 2027).
Sources
- Commercial Payments Bill [HL], bills.parliament.uk/bills/4128: stages; HL Bill 55 as amended on report (sections 2B to 2E, 6A, 113B to 113D, and the SBC scheme).
- GOV.UK, “Largest crackdown on late payments in over 25 years”, 19 May 2026 (£11 billion, 38 businesses a day, 8% interest, board and audit committee intention).
- Gowling WLG, “The Commercial Payments Bill: a closer look at the proposed ban on retentions”, 14 October 2026.
- Pye Tait Consulting for BEIS, Retention payments in the construction industry, 2017.
- BEIS, Retention payments in the construction industry: summary of responses, 2020.
- Oo, Lim and Runeson, “Critical factors affecting contractors’ decision to bid: a global perspective”, Buildings 12, 379, 2022.
- Insolvency Service, company insolvency statistics, January 2026 (construction the highest sector; specialist trades 56% of construction cases).
- The 5 to 10% pricing gap is the author’s own experience. No published study measures it.
Andy Pritchard MCIOB
CIOB Gold Medal, Construction Manager of the Year 2019. Founder of Constructing Culture and author of Going for Gold. About Andy →